The planned timeline for the Environmental Impact Statement (EIS) for the Ground Based Strategic Deterrent (GBSD) deployment and Minuteman III decommissioning and disposal project extends from 2020 to 2023.

GBSD EIS Major Milestone Schedule

Event / Month, Year

  • Notice of Intent published / September, 2020

  • Public scoping period / September–November, 2020

  • Draft EIS published / Summer, 2022

  • Draft EIS public comment period / Summer, 2022

  • Draft EIS public hearings held / Summer, 2022

  • Final EIS published / Spring, 2023

  • Record of Decision completed / Spring-Summer, 2023