The planned timeline for the Environmental Impact Statement (EIS) for the Ground Based Strategic Deterrent (GBSD) deployment and Minuteman III decommissioning and disposal project extends from 2020 to 2023.
GBSD EIS Major Milestone Schedule
GBSD EIS Major Milestone Schedule
Event / Month, Year
Event / Month, Year
Notice of Intent published / September, 2020
Public scoping period / September–November, 2020
Draft EIS published / Summer, 2022
Draft EIS public comment period / Summer, 2022
Draft EIS public hearings held / Summer, 2022
Final EIS published / Spring, 2023
Record of Decision completed / Spring-Summer, 2023